Zheleznogorsk
Aluminum composite panels
"We will work" - Roman Galiev, the General Director of the Alucom factory

Title

Purchase of the second production line of aluminum composite panels.
Objectives

The main project objective is to purchase the second production line of aluminum composite panels (ACP) of "Alukom" with the thickness of 3 mm. It will help to improve the quality of manufactured products and increase the sales volume. Thus, as a result of the project implementation "Alukom" will:

  • keep the market share it has among producers of ACP;
  • create additional 55 jobs, including at least 30 for former employees of MCK.
Summary

The aim of the project was to establish the production of, and to market, fire-resistant aluminium composite fa?ade panels on Alukom's Zheleznogorsk production site.

As a consequence of the company's mid-term sales and production plans, the company managed to purchase and launch a new production line for aluminium composite fa?ade panels, which is being used for the production of fire-resistant panels (Russian flammability category G1). Composite panels are composed of seven layers of different materials on two sides of a high-pressure polyethylene base (2-3 mm), an aluminium sheet (0,2 to 0,5 mm), an adhesive coating made of high-pressure polyethylene, a grounding layer, another aluminium sheet (0,2 to 0,5 mm), a working coating made of polyester on one side, a surface coating of polyvinyl fluoride (PVDF) and a protection film (to be peeled off after the fa?ade is installed).

A final audit of the project proved that the Beneficiary's obligations for job creation were overfulfilled (73 jobs /29 for ex-nuclear workers created vs 55 /30 planned initially).

The project is considered to have been completed successfully.

Cost

Total cost of the project is £723,000. The DECC's contribution is £200,000.
Duration

18 months - from 31 March 2007 till 30 September 2008.
Beneficiary

Rolling Plant "Alukom" Ltd., Zheleznogorsk