UK-Russia Closed Nuclear Cities Partnership
United Kingdom - Russia
Closed Nuclear Cities Partnership

Snezhinsk
Facility to manufacture metalworking equipment
Practical Outcomes of Project Realization

Title

Setting up a production facility to manufacture metalworking equipment.
Objectives

The main objective of the project is to set up a production facility in Snezhinsk to manufacture high-tech metal-cutting tools. The project will:

  • Aim to meet 20% of Urals market in high-tech metal-cutting tools.
  • Create 18 new jobs, 11 of them former employees of RFNC-VNIITF.
Summary

Final audit showed that the Beneficiary had fulfilled all of its obligations in full. Job creation were over fulfilled (18 jobs /12 for former employees of VNIITF created vs 18/11 planned).

The project has been been completed successfully.

Cost

Total cost of the project is £330,306. The DECC's contribution is £185,000.
Duration

36 months - starting February 2006
Beneficiary

UralPromComplect Ltd, Snezhinsk