The existing INP facilities required adaptation to process production quantities (tons) of
gemstones:
- Purchase of new sources to upgrade the gamma irradiation facility.
- Purchase of new equipment to handle the throughput of gemstones required.
- Provision of a secure room in which to store the gemstones during the manufacturing process.
- Precisely define the irradiation and other conditions required to achieve marketable colours.
- Confirm that the gemstones will not fade.
- Finalise commercial contracts with the two companies already identified.
The Beneficiary fulfilled their obligations in full and overfulfilled their obligations in what
concerns new jobs creation. 30 jobs were created / of which 30 are for the ex-weapon staff, 30/17 jobs were planned initially.
The project is considered to have been completed successfully.